After the Nov. 1 floods, Arizona leaders asked the Army Corps to keep Rio de Flag on schedule. Here's what Phase 4 involves, plus two other major Southwest projects named this month.
Fleet Intel with Steve · Issue #2 · Public Sector
The gist
- Heavy rain flooded parts of Flagstaff on Nov. 1. KJZZ reports the flooding caused two deaths and extensive property damage.[1]
- Sens. Mark Kelly and Ruben Gallego and Reps. Greg Stanton and Eli Crane signed a letter asking the U.S. Army Corps of Engineers to award the Rio de Flag construction contract by March 2027, as planned.[1][2]
- On Nov. 19, the Corps' Los Angeles District posted a presolicitation notice for Phase 4. It estimates the work at $35 million to $50 million. The solicitation is expected around Dec. 4, with a virtual bid opening around Feb. 11, 2027. As of Nov. 27, only the presolicitation was posted.[3]
The project
KJZZ reports the Rio de Flag Flood Control Project is meant to protect about 1,500 structures in a flood plain on Flagstaff's Southside. It was first authorized in 2000 and has been reauthorized twice as costs grew. The project is now estimated at $244 million, with the city paying 35% and the Corps covering the rest. The city has already spent $12.5 million on smaller resilience features.[1]

What Phase 4 involves
From the Corps' Nov. 19 notice:[3] - About 4,950 linear feet of work, including roughly 1,995 feet of reinforced concrete box culverts and 2,555 feet of riprap-lined channel. - About 85,000 cubic yards of soil excavation, 27,000 of soft rock and 21,000 of hard basalt. The hard rock needs line drilling and controlled blasting under strict vibration limits. - Culvert work within 15 feet of the active BNSF main line, with automated monitoring of vibration and ground movement. - Removal of petroleum-contaminated soil and old underground storage tanks downtown, plus city water, sewer and storm-drain relocations. - A period of 1,095 calendar days from notice to proceed, including expected winter shutdowns in December and January. - An unrestricted, sealed-bid contract awarded to the lowest-priced responsive, responsible bidder. The notice lists a 20% bid guarantee (capped at $3 million), 100% performance and payment bonds, Davis-Bacon wages and a project labor agreement.
For fleets
A three-year downtown heavy civil job means haul trucks, water trucks, utility crews and traffic control in and around the BNSF corridor. Contractors planning to bid should watch SAM.gov for the solicitation and amendments.[3]
Also new: two more major Southwest projects
Like this? Get Fleet Intel free every Saturday: subscribe here.
SR 24 Gateway Freeway awarded ($267.9 million)
The Arizona State Transportation Board awarded the SR 24 and Loop 202 widening job to FNF Construction, Inc. on Nov. 20 for $267,876,760.60. The work covers Mesa, Gilbert, Queen Creek, Maricopa County and Pinal County. It adds general-purpose lanes, builds new system ramps between Loop 202 and SR 24, and rebuilds Ironwood Drive as a diverging diamond interchange.[4] Details are in this issue's Bids story.
SpaceX's proposed Cochise County AI campus (not approved)
- What's proposed: a $50 billion, roughly 747-acre campus along U.S. 191 near the Apache Generating Station, outside the town of Cochise. It would have nine buildings to train SpaceX's AI models, plus battery storage and electrical and cooling systems.[5]
- Power and grid: the campus could eventually need up to 6 gigawatts, nearly 20% of Arizona's current generating capacity. SpaceX says it would fund about $3.6 billion in grid upgrades and a battery system storing up to 24 gigawatt-hours.[5] The first phase would be about 1.5 gigawatts, built in stages, according to the electric co-op that would serve it. Any power agreement still needs state regulators' approval.[7]
- Water: SpaceX says it would use a dry-cooling system needing about 7 to 10 acre-feet of water a year at full build-out, and would not use groundwater for industrial cooling.[5]
- Jobs: SpaceX estimates 5,500 construction jobs and 1,000 permanent jobs (see this issue's Jobs story).[5][6]
- Concerns: Arizona Attorney General Kris Mayes asked the county to delay its vote until state and federal reviews are done, citing the grid, water, public safety, transportation, wildlife and national security. Nearby residents have raised groundwater, noise, dust and emergency-services questions.[5]
Timeline and what to expect (as of Nov. 27; "Done" and "Scheduled" are confirmed by public records, "Estimate" rows are official or company projections) | Date | Step | Status | |---|---|---| | Nov. 19, 2026 | AG Mayes letter asks Planning and Zoning to postpone its vote[5] | Done | | Nov. 20, 2026 | Board chair Frank Antenori says SpaceX pledged no groundwater use, $3.6 billion in grid upgrades and compliance with dark-sky rules[6] | Done | | Dec. 3, 2026 | AG town hall, 5:30–7 p.m., Cochise Elementary School gym[5][7] | Scheduled | | Dec. 9, 2026 | County Planning and Zoning Commission considers the special use permit (SU26-22); its decision is final unless appealed to the Board of Supervisors[5][8] | Scheduled (county notice) | | About April–May 2027 | County's estimate for finishing land use, a development agreement and a building permit[6] | Estimate (county chair) | | Spring 2027 | Construction start, with the first stage possibly online three to six months later, per the co-op's plan as reported by AZPM[7] | Estimate (applicant/co-op plan) |
For fleets: if it's approved, a build this size in rural Cochise County would mean years of heavy hauling, utility and electrical crews along U.S. 191 and I-10.
Sources
- KJZZ. "Arizona leaders press feds on delayed Flagstaff flood infrastructure improvements." Nov. 22, 2026. https://www.kjzz.org/fronteras-desk/2026-11-22/arizona-leaders-press-feds-on-delayed-flagstaff-flood-infrastructure-improvements
- City of Flagstaff. Letter from the Arizona congressional delegation to the Acting Assistant Secretary of the Army (Civil Works). Nov. 18, 2026. https://www.flagstaff.az.gov/DocumentCenter/View/96754/11182026_AZ-Delegation-Rio-de-Flag-Letter
- U.S. Army Corps of Engineers, Los Angeles District. Presolicitation W912PL27BA001, "Rio De Flag – Phase 4 Construction." Posted Nov. 19, 2026. https://sam.gov/workspace/contract/opp/4a6ff6eb6239431b8722ff7d56c9ffd0/view
- Arizona Department of Transportation. "November 20, 2026 – Transportation Board Project Awards." https://aztransportationboard.gov/sites/default/files/2026-11/Awards-2026112026.pdf
- 12News (Maria Staubs). "What to know about SpaceX's massive, proposed data center in southeastern Arizona." Nov. 20, 2026. https://www.12news.com/article/news/local/arizona/spacexs-massive-proposed-data-center-southeastern-arizona-wilcox-cochise-county/75-3c7dcd2c-a864-4777-8bf1-951cef11a399
- Arizona's Family (Amy Cutler). "Cochise County chair reveals what SpaceX promised for $50 billion data center." Nov. 20, 2026. https://www.azfamily.com/2026/11/21/cochise-county-chair-reveals-what-spacex-promised-50-billion-data-center/
- AZPM (Katya Mendoza). "AG Mayes asks Cochise County officials to delay vote on planned SpaceX data center permit." Nov. 23, 2026. https://www.azpm.org/datacenters/2026-11-23/ag-mayes-asks-cochise-county-officials-to-delay-vote-on-planned-spacex-data-center-permit
- Cochise County Development Services. "Data Centers" (SU26-22 application status). Updated Nov. 12, 2026. https://www.cochise.az.gov/1014/Data-Centers
All sources accessed Nov. 22–27, 2026.
← Back to Issue #2: all stories
Meet Steve
I’m Steven Nohrden, Commercial/Government Account Manager for Ford Vehicle Sales with Chapman Ford Pro Elite in Scottsdale. I work with construction, trades, mining and government fleets across Arizona and the Southwest. Your business creates a ton of stress; my job is to make sure your vehicles are not one of the stressors.
“With Steve, the answer’s yes, what’s the question so I can get it done.” Hit reply on any issue and tell me what you need.
Fleet Intel with Steve is an independent newsletter written by Steven Nohrden. It is not sponsored, endorsed or published by Ford Motor Company or Ford Pro, and the views are my own. Ford and its model names are trademarks of Ford Motor Company, used only to identify products and news. Researched and drafted with help from Steven Nohrden’s SI personal assistant (Grok Bot). Steve reviews every issue, but mistakes are possible; please check the linked sources. Not legal or compliance advice. © 2026 Steven Nohrden.